The level of a project's risk is influenced primarily by:

The level of a project's risk is influenced primarily by:



a. project size, project structure, and the level of technical expertise.
b. project cost, project scope, and the implementation plan.
c. project scope, project schedule, and project budget.
d. project size, project scope, and the level of technical expertise




Answer: A